All Projects

Project
Office
Budget
Progress
Action
Default Image

Construction of Blacktop Road with Cross and Side Drainage Works on Krishnanagar - Sirsihawa - Balanagar - Laalpur - Jhulaniya - Choraha, Kapilvastu

सडक डिभिजन, कपिलवस्तु

Rs. 15,65,33,182

27.00%

Default Image

Design and Build of Bridge over Raising Khola, Arghakhanchi

डिभिजन सडक कार्यालय, दोलखा

Rs. 9,89,57,000

22.87%

Default Image

Construction of Steel Truss Bridge over Western Koshi Canal (1no*55 m Span, Total Length 55.9 m) along M.R.M Traffic Chowk Banainiya Road, Saptari

हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी

Rs. 9,46,78,848

0.00%

Default Image

Road Rehabilitation Gurje-Chhahare Section of Samakhushi-Tokaha-Bidur Road (NH40), Nuwakot

डिभिजन सडक कार्यालय, मकवानपुर

Rs. 62,52,954

28.00%

Default Image

Roadway excavation improvement up to gravel top standard

Puspalal (Midhill) Road Project, Panchthar

Rs. 67,48,84,171

0.00%

Default Image

Rehabilitation/Post monsoon works along Mahakali Highway (Phaltude to Shahukhark section)

सडक डिभिजन, दाङ्ग

Rs. 6,60,59,087

40.00%

Default Image

Rapti Highway Ameliya-Tulsipur-Shitalpati Road (Ch 52+000 to 56+000) in Salyan District.

सडक डिभिजन, दाङ्ग

Rs. 3,04,62,088

50.00%

Default Image

Road Upgrading Works in Kaligandaki Corridor , Harmichaur-Balewa Section (CH. 185+000 KM to 229+480 KM),Gulmi,Baglung

सडक विभाग, काठमाण्डौ

Rs. 2,94,72,85,811

28.00%

Default Image

Araniko Highway (Jure-Kothe) Road Improvement

डिभिजन सडक कार्यालय, दोलखा

Rs. 4,59,28,362

98.00%

Default Image

CONSTRUCTION OF PRESTRESSED RCC BRIDGE OVER LASURI KHOLA ALONG HULAKI RAJMARG DANG

हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वाके

Rs. 12,55,32,529

30.00%

Default Image

Road Maintenance in Bitthad-Kalangagad Section of Khodpe Chainpur Highway (NH64)

सडक डिभिजन, बैतडी

Rs. 72,34,535

0.00%

Default Image

Construction of Basai Khola Bridge Janakpur Dhalkebar Road

Janakpur Parikrama, Byparik Margha Bistaar Yojana (Jatahi-Janakpur), Mahottari

Rs. 12,47,97,542

0.00%

Default Image

Improvement of Tallo Garjamini -Asaina- Sikalpatti - Thada- Janapuri -Dhakaniya- Ranipur- Basantapur- Bansaha - Ganeshpur -Deepnagar -Amarpur- Naukhari -Manikapur dham road, Kanchanpur (Bansaha to Ganeshpur, Chainage -0+000 to 2+025 )

सडक डिभिजन, कञ्चनपुर

Rs. 97,18,994

100.00%

Default Image

Construction of Iwa Khola

डिभिजन सडक कार्यालय, ईलाम

Rs. 5,21,74,504

0.00%

Default Image

Rehabilitation Works on Syaubari Dhunche Section of Balaju-Trisuli- Dhunche-Shyaphru Road ,Rasuwa (NH18)

डिभिजन सडक कार्यालय, नुवाकोट

Rs. 55,45,480

0.00%

Default Image

Improvement of Tikapur- Dudejhari MRM Road, Kailali

सडक डिभिजन, कञ्चनपुर

Rs. 21,28,110

100.00%

Default Image

Road Upgrading Works along Guthi Prasauni - Ratangunj -Narsahi - Shrinagar - Kudiya Road(Ch.00+000 to 09+990)

सडक डिभिजन, वुटवल

Rs. 21,01,41,392

28.00%

Default Image

Construction of Earthwoks, Gravel & RCC Road Works along six laneko highway singerjoda hudai Mujeliya samm Jodne Sadak, Dhanusha (RDJKR/33701143/077-78/51)

डिभिजन सडक कार्यालय, धनुषा

Rs. 80,81,485

0.00%

Default Image

Road Upgrading Works on Banepa Panauti Road Kavre (Ch. 2+200 - 3+900)

सडक डिभिजन, भक्तपुर

Rs. 4,11,84,063

100.00%

Default Image

Mahendra Rajmarg. (Chandrauta-Shivapur chok Section), Kapilvastu

सडक डिभिजन, कपिलवस्तु

Rs. 1,10,33,641

0.00%

Default Image

Rehabilitation Works of Post Monsoon Damaged Section on Surkhet-Dailekh(Ch:50+000 to 66+000)

हेभिईक्युपमेन्ट डिभिजन, कैलाली

Rs. 97,31,770

26.00%

Default Image

Recurrent maintenance works along Dhansar-Patalaiya-Chure section of MRM

डिभिजन सडक कार्यालय, मकवानपुर

Rs. 30,56,000

0.00%

Default Image

Construction of Blacktop (Asphalt Concrete), RCC Road ,Box Culvert & Hume Pipe Culvert works along Sapahi bazaar bhuisthan mandir rastriya dhanbali uttar chheu prastoki Ma. Vi. Ko sirsiya purbi tole sadak,Dhanusha

डिभिजन सडक कार्यालय, धनुषा

Rs. 1,67,52,675

0.00%

Default Image

Road Improvement Works on Bayarghari Banethok Deurali Biruwa Road,Syangja

डिभिजन सडक कार्यालय, नुवाकोट

Rs. 33,52,234

26.00%

Default Image

Construction of PSC 2-Webbed RCC Bridge over Jalad River along Kachuri- Nayatol Katrait Sadak, Dhanusha

डिभिजन सडक कार्यालय, धनुषा

Rs. 15,49,34,963

52.00%

Default Image

Highway Upgrading and Rehabilitation Works along Rapti Highway Shitalpati- Musikot Road (Mokhla to Bagchaur section) in Salyan District.

सडक डिभिजन, दाङ्ग

Rs. 1,03,67,971

0.00%

Default Image

राप्ती हाईवे लुहाम लान्ती सडक खण्ड सल्यान ।

सडक डिभिजन, दाङ्ग

Rs. 41,17,950

0.00%

Default Image

Upgrading and Rehabilitation works along Lubhu-Lakuribhanjyang-Manedovan Road

डिभिजन सडक कार्यालय, ललितपुर

Rs. 3,04,09,646

0.00%

Default Image

Upgrading to Gravel Road Standard of Chatara-Mulghat-Majhitar-Dovan-Olangchunggola (Tamor Corridor) Road, Dagurne-Thiwa Section (Chainage 135+000 to 151+500 Km)

उत्तर दक्षिण (मुलघाट दोभान ओलाङ्चुङगोला खण्ड​) सडक योजना, ताप्लेजुङ्ग

Rs. 21,49,55,282

25.68%

Default Image

Roadway Improvement Work (Widening and Structural Work) along Karnali Ragmarga NH-59 (Dahikhola Khulalu Section )

डिभिजन सडक कार्यालय, ईलाम

Rs. 84,63,190

10.77%

Default Image

Reactive (Recurrent) Maintenance of Road Surface. in Khodpe-Chainpur Highway, Ch: 0+000 to 108+000 (NH-64)

सडक डिभिजन, बैतडी

Rs. 73,45,007

0.00%

Default Image

Road Upgrading Works along Soudikula Simalbutta Uttar Amrai Siswani Thantigaun Rajoura Shahipur Bijouri Danda Rolpa Holeri Road, Dang (Ch Km 0+000 to 3+900).

Unknown

Rs. 16,25,29,526

30.00%

Default Image

Construction of box Culvert along Laxminiya ga.pa.wad no 07 tole dekhi Laxminiya mai Mandir samma Sadak Dhanusha.

सडक डिभिजन, वांके

Rs. 57,66,485

25.00%

Default Image

Road Improvement Works on Chandrapur Na.Pa. Santpur dekhi Brindawan Na.Pa. ra Gadhimai Na.Pa.01 hudai Garuda Na.Pa. ko Birta Chok Paschim Pattiko Sadak hudai Bhusaha hudai wada Aurahi hudai Bargajwa Akarpatar hudai Huseni Chok Narkatiya Bhawanipur hudai Hardiya Road

डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर

Rs. 10,81,56,022

27.00%

Default Image

Construction of pedestrian crossing overhead bridge at sanepa -Balkhu

काठमाडौं चक्रपथ सुधार योजना, ललितपुर

Rs. 3,70,99,491

0.00%

Default Image

Rehabilitation Works along Duhabi Inaruwa Road, Sunsari

डिभिजन सडक कार्यालय, मोरङ

Rs. 3,60,15,710

24.00%

Default Image

Construction of RCC Bridge over Sahaja Khola and Box Culvert 5*4 at Aurahi Ga.Pa.-1, Siraha

सडक डिभिजन, तनहुं

Rs. 10,21,38,084

25.00%

Default Image

Road Upgrading Works on ARM Indrasan Party Palace Ram Mandir Hanumante Khola Road- Madhyapur Thimi 1

सडक डिभिजन, भक्तपुर

Rs. 31,89,730

30.00%

Default Image

Upgrading and Improvement Works on Mahendra Rajmarg. (Gorusinghe Bazar (CH. 634+000)-Dhan khola (CH-675+000) Section), Kapilvastu

सडक डिभिजन, कपिलवस्तु

Rs. 99,68,088

0.00%

Default Image

Extension of Dholahiti-Sunakothi-Chapagaun-Pyanggau-Lele-Tileshwor hundai Saraswotikunda Road (Ch. 0+000-3+200)

काठमाण्डौ उपत्यका सडक विस्तार आयोजना, काठमाण्डौ

Rs. 20,63,81,324

35.00%