Contract Agreement Amount
Rs. 21,49,55,282
Physical Progress
25.68%
Financial Progress
25.74%
Remaining Payment
Rs. 74
Upgrading to Gravel Road Standard of Chatara-Mulghat-Majhitar-Dovan-Olangchunggola (Tamor Corridor) Road, Dagurne-Thiwa Section (Chainage 135+000 to 151+500 Km)
Office: उत्तर दक्षिण (मुलघाट दोभान ओलाङ्चुङगोला खण्ड) सडक योजना, ताप्लेजुङ्ग (288)
Fiscal Year: 078-79
Contract Date: 24-Oct-21
Start Date: 24-Oct-21
Completion Date: 24-Oct-2023 (EOT Not Done)
Project Description
No description available.