Contract Agreement Amount

Rs. 84,63,190

Physical Progress

10.77%

Financial Progress

25.64%

Remaining Payment

Rs. 74

Roadway Improvement Work (Widening and Structural Work) along Karnali Ragmarga NH-59 (Dahikhola Khulalu Section )

Office: डिभिजन सडक कार्यालय, ईलाम (12)

Fiscal Year: 080-81

10.77%

Contract Date: 9-Oct-23

Start Date: 9-Oct-23

Completion Date: 08-Oct-2024 (EOT Not Done)

Project Description

No description available.