Contract Agreement Amount
Rs. 10,21,38,084
Physical Progress
25.00%
Financial Progress
25.34%
Remaining Payment
Rs. 74
Construction of RCC Bridge over Sahaja Khola and Box Culvert 5*4 at Aurahi Ga.Pa.-1, Siraha
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 078-79
Contract Date: 1-Dec-22
Start Date: 1-Dec-22
Completion Date: 01-Dec-2024 (EOT Not Done)
Project Description
No description available.