Contract Agreement Amount
Rs. 3,70,99,491
Physical Progress
0.00%
Financial Progress
25.40%
Remaining Payment
Rs. 74
Construction of pedestrian crossing overhead bridge at sanepa -Balkhu
Office: काठमाडौं चक्रपथ सुधार योजना, ललितपुर (172)
Fiscal Year: 074-75
Contract Date: 12-Jul-17
Start Date: 12-Jul-17
Completion Date: 03-Oct-2022 (EOT Done)