Contract Agreement Amount
Rs. 9,46,78,848
Physical Progress
0.00%
Financial Progress
26.86%
Remaining Payment
Rs. 73
Construction of Steel Truss Bridge over Western Koshi Canal (1no*55 m Span, Total Length 55.9 m) along M.R.M Traffic Chowk Banainiya Road, Saptari
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)
Fiscal Year: 072-73
Contract Date: 29-May-16
Start Date: 29-May-16
Completion Date: 10-Jul-2023 (EOT Done)
Project Description
No description available.