Contract Agreement Amount

Rs. 2,94,72,85,811

Physical Progress

28.00%

Financial Progress

26.70%

Remaining Payment

Rs. 73

Road Upgrading Works in Kaligandaki Corridor , Harmichaur-Balewa Section (CH. 185+000 KM to 229+480 KM),Gulmi,Baglung

Office: सडक विभाग, काठमाण्डौ (2)

Fiscal Year: 079-80

28.00%

Contract Date: 12-Dec-22

Start Date: 12-Dec-22

Completion Date: 10-Dec-2025 (EOT Not Done)

Project Description

No description available.