Contract Agreement Amount
Rs. 67,48,84,171
Physical Progress
0.00%
Financial Progress
26.73%
Remaining Payment
Rs. 73
Roadway excavation improvement up to gravel top standard
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 074-75
Contract Date: 11-May-18
Start Date: 11-May-18
Completion Date: 08-Apr-2022 (EOT Done)
Project Description
No description available.