Contract Agreement Amount

Rs. 9,89,57,000

Physical Progress

22.87%

Financial Progress

26.92%

Remaining Payment

Rs. 73

Design and Build of Bridge over Raising Khola, Arghakhanchi

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 077-78

22.87%

Contract Date: 23-Jul-21

Start Date: 23-Jul-21

Completion Date: 19-Apr-2024 (EOT Not Done)

Project Description

No description available.