All Projects
Project |
Office |
Budget |
Progress |
Action |
|---|---|---|---|---|
|
Road Rehabilitation works on Sanfe-Balde Road Section (CH. 00+000~39+000) |
डिभिजन सडक कार्यालय, साँफेवगर, अछाम |
Rs. 2,34,84,237 |
50.00% |
|
|
Construction of 2-Webbed 50m RCC Motorable Bridge (2*25m) with pile foundation over Bhutaha Khola,Dhanusha |
सडक डिभिजन, डोटी |
Rs. 7,19,38,992 |
36.00% |
|
|
Construction of T-Beam RCC Bridge over setumari at Topgachhi jhapa |
डिभिजन सडक कार्यालय, झापा |
Rs. 2,23,97,914 |
0.00% |
|
|
Construction of Causeway, Retaining Works,Blacktop Works Along Mulkot-Amare Road Sindhuli |
डिभिजन सडक कार्यालय, खुर्कोट |
Rs. 1,41,19,905 |
40.00% |
|
|
Simbesi Golang Aagnichowk Belung Bhanjyang Phulkharka Ghumti Road, Dhading |
Unknown |
Rs. 24,15,96,837 |
38.00% |
|
|
Construction of Blacktopped Road at Damak-Krishna Mandir-Pingdanda-Dharanetole-Satomara-Aambari hudai Itahara Road |
डिभिजन सडक कार्यालय, झापा |
Rs. 95,69,377 |
0.00% |
|
|
Extension of Cross-Drainage Structures of Mahendra Highway (Chainage-1014+000 to 1027+000), Kanchanpur |
सडक डिभिजन, कञ्चनपुर |
Rs. 2,40,74,601 |
45.00% |
|
|
Upgrading of Narayan Chowk-Triveni Road, Nawalparasi |
हुलाकी राजमार्ग योजना कार्यालय, कपिलवस्तु |
Rs. 50,99,79,360 |
35.00% |
|
|
Road Improvement Works on India Border(Dodhara Chandani) Sundarpur Baitifanta Shivmandir Kalagad Babathan Bayalband Road, Kanchanpur |
सडक डिभिजन, कञ्चनपुर |
Rs. 23,33,09,063 |
80.00% |
|
|
Construction of Bridge over Bhaluhi Nadi along Tilakpur ward no.5,6 & Ramnagar 7 Misrauli Sadak in Nawalparasi District Prestressed Concrete Bridge (3x40m) |
सडक डिभिजन, वुटवल |
Rs. 8,07,82,445 |
100.00% |
|
|
Construction of Pavement (DBSD) and drains along langadi tinvati langadi ma vi jaganathpur 3+080 |
डिभिजन सडक कार्यालय, मकवानपुर |
Rs. 5,01,69,621 |
0.00% |
|
|
Roadway Excavation of Martadi Kolti Kawadi Bichhyasain Road, Bajura Section |
डिभिजन सडक कार्यालय, साँफेवगर, अछाम |
Rs. 87,01,066 |
50.00% |
|
|
Upgrading works of Gairitand-Kamalbazar-Turmakhand-Jungleghat-Babiyachaur-Chisapani Road Section, Achham |
डिभिजन सडक कार्यालय, साँफेवगर, अछाम |
Rs. 71,59,095 |
36.52% |
|
|
Bituminous Pavement work with Structural works from Kaptane (26+000 km) to Num (39+000) along Khandbari Kimathanka RoadBituminous Pavement work with Structural works from Khadbari(Loving Hill) to Thamserkhu 0+000 to 14+000 km |
उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा |
Rs. 28,83,88,121 |
35.00% |
|
|
Specific Maintenance works along surkhet-Jumla Road (Chainage 72+000-75+100) |
संपत्ती व्यवस्थापन ठेक्का व्यवस्थापन तथा गुणस्तर नियन्त्रण आयोजना, ललितपुर |
Rs. 63,32,280 |
37.00% |
|
|
Construction of Prestressed R.C.C Girder Bridge with Pile Foundation over Lalbakaiya River at Tikuliya, Rautahat |
डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर |
Rs. 14,92,12,106 |
0.00% |
|
|
Construction of Double Cell RC Box Culvert along Balara Kharahiya Tole Road, Sarlahi |
डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर |
Rs. 70,09,746 |
38.00% |
|
|
Construction of Ghamir Khola Bridge (1*15m) along Tamghas-Simaltari Section of Madan Bhandari Highway, Gulmi District |
तम्घास सिमल्टारी प्युठान सडक आयोजना, गुल्मी |
Rs. 2,77,73,659 |
50.00% |
|
|
Road Upgrading Works Along Mechi HIghway Ilam Na.Pa.-06 Eklebar Thuttebar Sadak (Eklebar-Thuttebar Section) |
डिभिजन सडक कार्यालय, ललितपुर |
Rs. 31,95,917 |
36.38% |
|
|
Upgrading/Improvement of Shahidmarga, Holeri-Tila Road Section (Ch 31+500 to 50+000) for DBST Standard |
शहीद मार्ग सडक योजना, रोल्पा |
Rs. 33,70,38,893 |
72.00% |
|
|
MIDHLPD/337011144/076/77 |
Puspalal (Midhill) Road Project, Dailekh |
Rs. 24,28,70,660 |
39.00% |
|
|
Upgrading of Mahendra (E/W) highway including construction of blacktop roads, pot holes repairing etc. Kamala Pushpalpur(Ch.236+620 to 257+200), Dhanusha |
डिभिजन सडक कार्यालय, धनुषा |
Rs. 1,74,67,622 |
85.00% |
|
|
Road Safety works at Harkapur Okhaldhunga Salleri Road Section |
योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) |
Rs. 3,50,20,000 |
0.00% |
|
|
Consruction of 3-Cell RCC Box Culvert at Charnath Uchhal Khola Sabaila-10,Dhanusha |
डिभिजन सडक कार्यालय, धनुषा |
Rs. 3,04,59,017 |
0.00% |
|
|
Design and Build of Kushumbaghat Bridge, Bardiya |
पुल योजना, पश्चिम क्षेत्र सेक्टर नं. ३, वांके |
Rs. 43,28,30,000 |
40.00% |
|
|
Road Upgrading Works of Charaudi Chauki Syadrul Solabhanja Rapti Na Pa Road, Dhading |
Unknown |
Rs. 22,60,27,169 |
38.00% |
|
|
Construction of Box culvert at Banigama-Laxmipur-Nikal sadak, Dhanusha |
डिभिजन सडक कार्यालय, धनुषा |
Rs. 2,45,52,394 |
0.00% |
|
|
Road Upgrading Works along Araniko Highway (Chalnedunga-Khawa-Lamidanda-Dolalghat) |
सडक डिभिजन, भक्तपुर |
Rs. 69,45,841 |
0.00% |
|
|
Construction of Bhalu Khola Prestressed Bridge, Lampantar ward no. 3 & 4, Sindhuli District in Chakmake-Jinakhu-KakurthakurKatari Road, Sindhuli |
डिभिजन सडक कार्यालय, खुर्कोट |
Rs. 4,00,11,718 |
41.00% |
|
|
Upgrading of Mugling Aanbukhaireni Pokhara Road (Section-1) (8+250 to 49+700) |
Unknown |
Rs. 5,49,83,30,511 |
38.00% |
|
|
Extension of Jorpati-Sundarijal Road (Ch. 0+000 to 3+500) |
काठमाण्डौ उपत्यका सडक विस्तार आयोजना, काठमाण्डौ |
Rs. 23,83,99,324 |
30.00% |
|
|
Road Structure and Pavement Construction Works on Kafaldanda Waling Gairasur Mandir Sadak, Syangja |
यान्त्रिक कार्यालय, चितवन |
Rs. 4,09,03,543 |
35.00% |
|
|
Road Upgrading works(Service Road Upgrading) on ARM Saanga-Dhulikhel (Chaiange: 19+800 to 30+000)- |
सडक डिभिजन, भक्तपुर |
Rs. 1,49,16,765 |
0.00% |
|
|
Improvement of Chisapani-Babiyachaur Road, Kailali |
सडक डिभिजन, कञ्चनपुर |
Rs. 42,49,150 |
100.00% |
|
|
सल्यान सालचौर-निगालचुला-माझखर्क-पाखापानी सडक |
सडक डिभिजन, दाङ्ग |
Rs. 3,22,823 |
0.00% |
|
|
Construction of Bidi Gad Bridge in Bajhang |
सेति लोकमार्ग (टिकापुर, लोडे, चैनपुर, ताक्लाकोट) सडक योजना, अछाम |
Rs. 4,69,11,851 |
45.00% |
|
|
Improvement of Pchchisghar Foolbari -Gadariya- Rajipur Road (0+750 To 1+010 ) |
सडक डिभिजन, कञ्चनपुर |
Rs. 97,60,286 |
80.00% |
|
|
Rigid Pavement Work along Nagma-Gamgadhi Road (Talcha-Gamgadhi Section) (RDJML/33701115/078/79-01) |
डिभिजन सडक कार्यालय, जुम्ला |
Rs. 8,45,35,355 |
35.73% |
|
|
Rigid Pavement Work along Nagma-Gamgadhi Road (Talcha-Gamgadhi Section) (RDJML/33701115/078/79-01) |
डिभिजन सडक कार्यालय, जुम्ला |
Rs. 8,45,35,355 |
35.73% |
|
|
Rehabilitation Works on Surkhet-Ranimatta Road (Ch. 25+000 to 50+000) |
सडक डिभिजन, सुर्खेत |
Rs. 4,65,19,720 |
98.50% |