Contract Agreement Amount
Rs. 2,40,74,601
Physical Progress
45.00%
Financial Progress
36.74%
Remaining Payment
Rs. 63
Extension of Cross-Drainage Structures of Mahendra Highway (Chainage-1014+000 to 1027+000), Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 077-78
Contract Date: 7-Jan-21
Start Date: 14-Jan-21
Completion Date: 09-Jul-2021 (EOT Not Done)
Project Description
No description available.