Contract Agreement Amount
Rs. 33,70,38,893
Physical Progress
72.00%
Financial Progress
36.37%
Remaining Payment
Rs. 63
Upgrading/Improvement of Shahidmarga, Holeri-Tila Road Section (Ch 31+500 to 50+000) for DBST Standard
Office: शहीद मार्ग सडक योजना, रोल्पा (93)
Fiscal Year: 076-77
Contract Date: 24-Feb-21
Start Date: 11-Mar-21
Completion Date: 23-Nov-2024 (EOT Done)
Project Description
No description available.