Contract Agreement Amount

Rs. 43,28,30,000

Physical Progress

40.00%

Financial Progress

36.21%

Remaining Payment

Rs. 63

Design and Build of Kushumbaghat Bridge, Bardiya

Office: पुल योजना, पश्चिम क्षेत्र सेक्टर नं. ३, वांके (190)

Fiscal Year: 077-78

40.00%

Contract Date: 25-Mar-21

Start Date: 25-Mar-21

Completion Date: 27-Sep-2024 (EOT Not Done)

Project Description

No description available.