Contract Agreement Amount

Rs. 4,69,11,851

Physical Progress

45.00%

Financial Progress

35.87%

Remaining Payment

Rs. 64

Construction of Bidi Gad Bridge in Bajhang

Office: सेति लोकमार्ग (टिकापुर​, लोडे, चैनपुर​, ताक्लाकोट​) सडक योजना, अछाम (197)

Fiscal Year: 074-75

45.00%

Contract Date: 2-Jul-18

Start Date: 2-Jul-18

Completion Date: 02-Jul-2020 (EOT Not Done)

Project Description

No description available.