Contract Agreement Amount
Rs. 1,49,16,765
Physical Progress
0.00%
Financial Progress
35.99%
Remaining Payment
Rs. 64
Road Upgrading works(Service Road Upgrading) on ARM Saanga-Dhulikhel (Chaiange: 19+800 to 30+000)-
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 7-Apr-21
Start Date: 7-Apr-21
Completion Date: 09-Jul-2021 (EOT Not Done)
Project Description
No description available.