Contract Agreement Amount

Rs. 3,22,823

Physical Progress

0.00%

Financial Progress

35.87%

Remaining Payment

Rs. 64

सल्यान सालचौर-निगालचुला-माझखर्क-पाखापानी सडक

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 072-73

0.00%

Contract Date: 2-Jun-16

Start Date: 5-Jun-16

Completion Date: 30-Sep-2016 (EOT Done)

Project Description