Contract Agreement Amount
Rs. 4,65,19,720
Physical Progress
98.50%
Financial Progress
35.71%
Remaining Payment
Rs. 64
Rehabilitation Works on Surkhet-Ranimatta Road (Ch. 25+000 to 50+000)
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 076-77
Contract Date: 3-Mar-20
Start Date: 6-Mar-20
Completion Date: 04-Mar-2021 (EOT Not Done)