Contract Agreement Amount

Rs. 4,65,19,720

Physical Progress

98.50%

Financial Progress

35.71%

Remaining Payment

Rs. 64

Rehabilitation Works on Surkhet-Ranimatta Road (Ch. 25+000 to 50+000)

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

98.50%

Contract Date: 3-Mar-20

Start Date: 6-Mar-20

Completion Date: 04-Mar-2021 (EOT Not Done)

Project Description

No description available.