All Projects
Project |
Office |
Budget |
Progress |
Action |
|---|---|---|---|---|
|
Blacktop works on Nagra (Indian Border) -Devistan -Mahakali Bridge Road , Kanchanpur |
सडक डिभिजन, कञ्चनपुर |
Rs. 27,66,200 |
100.00% |
|
|
Recurrent Maintainance Works on Koshi Highway (Hile-Basantpur) |
डिभिजन सडक कार्यालय, धनकुटा |
Rs. 31,68,016 |
0.00% |
|
|
Excavation of Roadway and Structural works on Dumre- Bhaisikatta- Budakholsa-Gahate- Sardewa-Saalmure road section |
सडक डिभिजन, पाल्पा |
Rs. 56,70,453 |
100.00% |
|
|
Road Improvement Works along Bhimphedi-1 Sanutar Madhyebaas Kisedi hudai Kailash Ghaitang jodne Road, Makwanpur |
डिभिजन सडक कार्यालय, दोलखा |
Rs. 35,03,837 |
100.00% |
|
|
ट्राफिक सेफ्टी कार्य म.रा.मा धानखोला शिवखोला । |
सडक डिभिजन, दाङ्ग |
Rs. 12,72,850 |
0.00% |
|
|
Construction of Prestressed RCC Bridge over Khadak Khola (4 No*35 m Span, Total Length 150 m) along Rajbiraj Balan, Hulaki Road, Saptari |
हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी |
Rs. 10,40,25,687 |
100.00% |
|
|
Improvement of Road by Construction of Gabion Structure |
सडक डिभिजन, कपिलवस्तु |
Rs. 13,95,000 |
100.00% |
|
|
Road Upgrading Works on Bohoredobaan-Thuloparsel-Chitretar-Mamti Sadak, Kavre |
सडक डिभिजन, भक्तपुर |
Rs. 46,44,264 |
0.00% |
|
|
Upgrading Worls along Bhojpur Sadarmukam Suntale Bazar Timma Hudai Temkemayung Ga.Pa. Kendra Annapurna Pandhare Okhre Dalgaun Hudai Bhojpur Sadarmukam (Ringroad) Chakrapath Bhojpur |
डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा |
Rs. 8,67,000 |
0.00% |
|
|
Roadway Excavation and Structrural works on Sanfebagar-04 Himalayan Ma. Vi. To Bimkot Road Section |
योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) |
Rs. 43,99,271 |
97.00% |
|
|
Design and Build of Bridges 2. Rapti Bridge, Jahare Connecting Satbariya VDC and Rajapur |
पुल योजना, पश्चिम क्षेत्र सेक्टर नं. ३, वांके |
Rs. 30,53,84,955 |
100.00% |
|
|
Road Improvement Works along MarchawarTunihawa to Bogadi- Bagauli to Ampas 2 lane Road Construction |
डिभिजन सडक कार्यालय, चितवन |
Rs. 37,55,040 |
100.00% |
|
|
Blacktopped Road Construction Works along Pokhariya Power Station dekhi Basantpur, Phulbariya Gau hudai Mukhya Nahar Road, Parsa |
डिभिजन सडक कार्यालय, ललितपुर |
Rs. 28,47,585 |
100.00% |
|
|
Rigid Pavement Works along Pokhariya ward no 10 Bahuarwa Tol dekhi Raniganj hudai Mahendra Path samma Road, Parsa |
सडक डिभिजन, तनहुं |
Rs. 35,36,175 |
100.00% |
|
|
Roadway Excavation,Structure and Gravelling works on Tallodungeshr-Satkhamb-Dullu-Pipalkot-Khulalu-Manma-Nagma Road(Chorsalla-Bhajaniya-Pokhari-Pyadura Section |
सडक डिभिजन, सुर्खेत |
Rs. 38,14,500 |
98.09% |
|
|
Construction of Slab Culvert at Simara Kaudena Khoirya Hempur Kishanpur Sadak, Sarlahi |
डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर |
Rs. 19,45,609 |
0.00% |
|
|
Road upgrading works on Mangaltar - Charkilla - Banakhu - Ghartichhap - Gokule - Molaiti Road, Kavre |
सडक डिभिजन, भक्तपुर |
Rs. 57,47,070 |
0.00% |
|
|
Laying of Hume Pipe and Gravelling works along Syuchatar Bridge to Swyambhu Ghumba (Right Side) |
काठमाडौं चक्रपथ सुधार योजना, ललितपुर |
Rs. 3,25,59,096 |
0.00% |
|
|
Earthwork, Graveling, Blacktop and Structure Works in Barahathwa-Samanpur-Katahariya-Kalaiya Sadak, Sarlahi, Rautahat, Bara( at Katahariya to Jhanj Bridge) Sadak, Sarlahi |
डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर |
Rs. 1,95,30,102 |
0.00% |
|
|
Specific Maintenance works on Bhotechour Chapali Road. |
डिभिजन सडक कार्यालय, दोलखा |
Rs. 31,58,225 |
0.00% |
|
|
Road Widening and Upgrading works on Bohoredobhan- Thuloparsel - Chitretar - Mamti Sadak, Kavre |
सडक डिभिजन, भक्तपुर |
Rs. 35,99,325 |
0.00% |
|
|
दोदा नदीमा पक्की पुल, नन्द गाउँ र बल्मी जोड्ने बाटोमा, कन्चनपुर |
पुल योजना, पश्चिम क्षेत्र सेक्टर नं. ३, वांके |
Rs. 35,03,42,300 |
100.00% |
|
|
Balchanpur jangalsaiya Kolbi Sadak, Rautahat |
डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर |
Rs. 27,58,751 |
0.00% |
|
|
Black Top and Cross Drainage works along Kawasoti 3 – Gumbachowk - Bhanuchowk, Sitalchowk - MaanechokhudaiTulsiChowk road, Nawalpur |
सडक डिभिजन, वुटवल |
Rs. 58,02,625 |
100.00% |
|
|
Roadway Upgrading Works on Sundar Bazaar Khatri Thanti Haandetar Kunchha bhanjyang Jitabeshi Road, Lamjung |
सडक डिभिजन, तनहुं |
Rs. 41,19,440 |
0.00% |
|
|
Widening of Yamdi Bridge-Ghatte khola Section of Pokhara Baglung Road (0+000 to 6+000 ) in Kaski District |
Puspalal (Midhill) Road Project, Parbat |
Rs. 86,83,63,300 |
100.00% |
|
|
Road Side Maintenance Along Mechi Highway (Taplejung-Gharilla Section) |
डिभिजन सडक कार्यालय, धनकुटा |
Rs. 14,18,035 |
100.00% |
|
|
Construction of Prestressed RCC Bridge over Budhikhola along Bhurigaun Gulariya Murtiya Road |
हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वाके |
Rs. 4,48,53,816 |
0.00% |
|
|
Road Gravelling and structural works on Chitre towards Sanfebagar Road Section (136+000 to 144+000) |
सेति लोकमार्ग (टिकापुर, लोडे, चैनपुर, ताक्लाकोट) सडक योजना, अछाम |
Rs. 3,55,52,248 |
98.06% |
|
|
Reactive Maintenance (Patch Works) Chaukhette Sanfe Road Section |
डिभिजन सडक कार्यालय, साँफेवगर, अछाम |
Rs. 19,56,250 |
0.00% |
|
|
Rehabilitation Work of Dumre-Besisahar Road ( Km. 26+260 to Km. 35+600) |
सडक डिभिजन, तनहुं |
Rs. 2,85,39,200 |
0.00% |
|
|
Rehabilitation and Improvement works along Mahalaxmi Campus Chowk Khahare Culvert Lalitpur Ghumti Road |
डिभिजन सडक कार्यालय, ललितपुर |
Rs. 11,84,200 |
0.00% |
|
|
Rehabilitation Work on MRM (Chapur Dhansar) Road, Rautahat |
डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर |
Rs. 2,43,46,357 |
100.00% |
|
|
Rigid Pavement & Drain work along Khandbari Badareni Khamare Wana Sadak Starronnati Chainage 0+000 km towards |
डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा |
Rs. 20,02,239 |
0.00% |
|
|
Bishrampur Sangrampur Sadak, Sarlahi |
डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर |
Rs. 45,30,000 |
0.00% |
|
|
Road upgrading works on Panauti- Khopasi – Taldhunga Road, Kavre |
सडक डिभिजन, भक्तपुर |
Rs. 39,66,900 |
0.00% |
|
|
Road Maintenance works on Chamasingh Amaldol Nala Banepa Road |
सडक डिभिजन, भक्तपुर |
Rs. 10,17,079 |
0.00% |
|
|
Potholes Maintenance Works with loose gravel on earthen road along Bheri Corridor-Rimna to Tallubagar, (Ch:16+000 to 20+000) |
डिभिजन सडक कार्यालय, चौरजहारी |
Rs. 5,15,468 |
0.00% |
|
|
Rehabilation Works on Koshi Highway (Dhankuta to Hile Section) |
सुदुरपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, डोटी |
Rs. 3,01,47,452 |
100.00% |
|
|
Construction of Prestressed bridge (4X40m) with Open Foundation Over Aaurahi Khola along Ranipur-Pratappur-Kaligaudi Road, Bardiya |
सडक डिभिजन, वांके |
Rs. 9,55,53,001 |
65.00% |