Contract Agreement Amount
Rs. 9,55,53,001
Physical Progress
65.00%
Financial Progress
98.03%
Remaining Payment
Rs. 1
Construction of Prestressed bridge (4X40m) with Open Foundation Over Aaurahi Khola along Ranipur-Pratappur-Kaligaudi Road, Bardiya
Office: सडक डिभिजन, वांके (32)
Fiscal Year: 073-74
Contract Date: 22-May-17
Start Date: 22-May-17
Completion Date: 15-Jan-2023 (EOT Done)
Project Description
No description available.