Contract Agreement Amount

Rs. 1,95,30,102

Physical Progress

0.00%

Financial Progress

98.08%

Remaining Payment

Rs. 1

Earthwork, Graveling, Blacktop and Structure Works in Barahathwa-Samanpur-Katahariya-Kalaiya Sadak, Sarlahi, Rautahat, Bara( at Katahariya to Jhanj Bridge) Sadak, Sarlahi

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 073-74

0.00%

Contract Date: 13-Jul-17

Start Date: 13-Jul-17

Completion Date: 15-Aug-2019 (EOT Done)

Project Description

No description available.