Contract Agreement Amount

Rs. 37,55,040

Physical Progress

100.00%

Financial Progress

98.09%

Remaining Payment

Rs. 1

Road Improvement Works along MarchawarTunihawa to Bogadi- Bagauli to Ampas 2 lane Road Construction

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 079-80

100.00%

Contract Date: 18-Dec-22

Start Date: 18-Dec-22

Completion Date: 18-Jun-2023 (EOT Not Done)

Project Description

No description available.