Contract Agreement Amount

Rs. 66,87,355

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Roadway Excavation and Gabion works at (Maurya Tripurakot Mustang Dolpa Section)

Office: डिभिजन सडक कार्यालय, चौरजहारी (181)

Fiscal Year: 078-79

0.00%

Contract Date: 1-Apr-22

Start Date: 8-Apr-22

Completion Date: 04-Jul-2022 (EOT Not Done)

Project Description

No description available.