Contract Agreement Amount
Rs. 25,40,87,816
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Road widening and upgrading of Balefi- Jalbire- Katike- Tembuthan Road, Sindhupalchowk (Chainage 5+000 to10+100)
Office: सडक डिभिजन, प्युठान (30)
Fiscal Year: 079-80
Contract Date: 15-Feb-23
Start Date: 15-Feb-23
Completion Date: 12-Feb-2025 (EOT Not Done)
Project Description
No description available.