Contract Agreement Amount

Rs. 1,28,28,979

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Road improvement works along Emlihawa-Piparhawa-Chamkipur-diyanagadh-Shankapur khaharni Rajmarg Rupandehi

Office: सडक डिभिजन, पोखरा (26)

Fiscal Year: 077-78

0.00%

Contract Date: 5-Jul-21

Start Date: 5-Jul-21

Completion Date: 05-Mar-2022 (EOT Not Done)

Project Description

No description available.