Contract Agreement Amount
Rs. 1,47,68,662
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Road extension of Thali Bhutepokhari Tamdanda Baguwa Gokarna Road
Office: डिभिजन सडक कार्यालय, काठमाण्डौ (22)
Fiscal Year: 075-76
Contract Date: 16-May-18
Start Date: 16-May-18
Completion Date: 16-May-2019 (EOT Not Done)
Project Description
No description available.