Contract Agreement Amount
Rs. 2,63,40,387
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Road Upgrading works on (Ch: 162+000 to 168+000) Road section of Seti Highway, Achham
Office: सडक विभाग, काठमाण्डौ (2)
Fiscal Year: 081-82
Contract Date: 23-Dec-24
Start Date: 23-Dec-24
Completion Date: 04-Jul-2025 (EOT Not Done)
Project Description
No description available.