Contract Agreement Amount

Rs. 80,98,388

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Road Improvement (Rigid Pavement )Works on TRP (Simbhanjang -Palung section)

Office: डिभिजन सडक कार्यालय, मकवानपुर (19)

Fiscal Year: 078-79

0.00%

Contract Date: 8-Apr-22

Start Date: 8-Apr-22

Completion Date: 10-Jul-2022 (EOT Not Done)

Project Description

No description available.