Contract Agreement Amount

Rs. 84,13,335

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Road Extension Works

Office: काठमाडौं चक्रपथ सुधार योजना, ललितपुर (172)

Fiscal Year: 071-72

0.00%

Contract Date: 30-Jun-15

Start Date: 30-Jun-15

Completion Date: 11-Dec-2015 (EOT Not Done)

Project Description

No description available.