Contract Agreement Amount
Rs. 67,80,573
Physical Progress
100.00%
Financial Progress
200.00%
Remaining Payment
Rs. -,100
Traffic Safety works (Installing W-Beam) on Chaukhutte-Sanfe-Mangalsen Road Section Achham (NH-03)
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 079-80
Contract Date: 16-Apr-23
Start Date: 16-Apr-23
Completion Date: 10-Jul-2023 (EOT Not Done)
Project Description
No description available.