Contract Agreement Amount

Rs. 67,80,573

Physical Progress

100.00%

Financial Progress

200.00%

Remaining Payment

Rs. -,100

Traffic Safety works (Installing W-Beam) on Chaukhutte-Sanfe-Mangalsen Road Section Achham (NH-03)

Office: सडक डिभिजन, पाल्पा (27)

Fiscal Year: 079-80

100.00%

Contract Date: 16-Apr-23

Start Date: 16-Apr-23

Completion Date: 10-Jul-2023 (EOT Not Done)

Project Description

No description available.