Contract Agreement Amount

Rs. 16,32,140

Physical Progress

0.00%

Financial Progress

192.96%

Remaining Payment

Rs. -92

Roadway Excavation and Gabion Wall Works on Jarkot-Barakhola-Deulkada-Ratapani-Bhapra Sadak Dailekh (C.No:RDSKT/33701137-4/077/78-3)

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 077-78

0.00%

Contract Date: 11-Nov-20

Start Date: 11-Nov-20

Completion Date: 14-Mar-2021 (EOT Not Done)