Contract Agreement Amount

Rs. 32,67,400

Physical Progress

100.00%

Financial Progress

175.20%

Remaining Payment

Rs. -75

Roadway Excavation structural works on Halesi Kartike Sunkoshi sadak starronati Halesi Tuwachung Na. Pa.

Office: डिभिजन सडक कार्यालय, ईलाम (12)

Fiscal Year: 079-80

100.00%

Contract Date: 15-Feb-23

Start Date: 15-Feb-23

Completion Date: 10-Jul-2023 (EOT Not Done)

Project Description

No description available.