Contract Agreement Amount

Rs. 57,17,878

Physical Progress

0.00%

Financial Progress

143.28%

Remaining Payment

Rs. -43

Road Improvement Works On Bidur Nuwakot Durbar Road, Nuwakot

Office: डिभिजन सडक कार्यालय, नुवाकोट (21)

Fiscal Year: 076-77

0.00%

Contract Date: 10-Feb-20

Start Date: 10-Feb-20

Completion Date: 15-Dec-2020 (EOT Done)

Project Description

No description available.