Contract Agreement Amount
Rs. 57,17,878
Physical Progress
0.00%
Financial Progress
143.28%
Remaining Payment
Rs. -43
Road Improvement Works On Bidur Nuwakot Durbar Road, Nuwakot
Office: डिभिजन सडक कार्यालय, नुवाकोट (21)
Fiscal Year: 076-77
Contract Date: 10-Feb-20
Start Date: 10-Feb-20
Completion Date: 15-Dec-2020 (EOT Done)
Project Description
No description available.