Contract Agreement Amount

Rs. 8,15,07,402

Physical Progress

94.00%

Financial Progress

133.29%

Remaining Payment

Rs. -33

Construction RCC Bridge Over Handi Khola, Sindhupalchowk

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 073-74

94.00%

Contract Date: 5-Jul-17

Start Date: 5-Jul-17

Completion Date: 31-Dec-2019 (EOT Not Done)

Project Description

No description available.