Contract Agreement Amount

Rs. 25,02,815

Physical Progress

55.00%

Financial Progress

124.12%

Remaining Payment

Rs. -24

Construction of Slab Culvert at Sarnamati - Khalingchowk to 9km Jange Pillar Sima Sadak, Jhapa

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 076-77

55.00%

Contract Date: 20-Nov-19

Start Date: 20-Nov-19

Completion Date: 13-May-2020 (EOT Not Done)

Project Description

No description available.