Contract Agreement Amount
Rs. 57,45,18,352
Physical Progress
100.00%
Financial Progress
123.61%
Remaining Payment
Rs. -23
Widening, Grade improvemnet, Drainage, Soiling, Structural Works and Sub-base works from Dovan, Nayabasti-Barun Road Section(53+000 to 80+000)
Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)
Fiscal Year: 075-76
Contract Date: 4-Jul-19
Start Date: 4-Jul-19
Completion Date: 03-Jul-2022 (EOT Not Done)