Contract Agreement Amount

Rs. 57,45,18,352

Physical Progress

100.00%

Financial Progress

123.61%

Remaining Payment

Rs. -23

Widening, Grade improvemnet, Drainage, Soiling, Structural Works and Sub-base works from Dovan, Nayabasti-Barun Road Section(53+000 to 80+000)

Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)

Fiscal Year: 075-76

100.00%

Contract Date: 4-Jul-19

Start Date: 4-Jul-19

Completion Date: 03-Jul-2022 (EOT Not Done)

Project Description

No description available.