Contract Agreement Amount

Rs. 4,11,06,400

Physical Progress

0.00%

Financial Progress

119.45%

Remaining Payment

Rs. -19

Back cutting, Grade Cutting ,Curve improvement soling works& structural works along Barun Hatiya section (80+000-97+000)

Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)

Fiscal Year: 076-77

0.00%

Contract Date: 18-Dec-19

Start Date: 1-Jan-20

Completion Date: 15-Dec-2020 (EOT Done)