Contract Agreement Amount
Rs. 10,70,03,629
Physical Progress
30.00%
Financial Progress
118.80%
Remaining Payment
Rs. -18
11 kilo chhepetar Bhaluswara Barpak Sadak Gorkha 22+000 to 30+0000
Office: गाेरखा सडक योजना, गोरखा (108)
Fiscal Year: 071-72
Contract Date: 16-Jul-15
Start Date: 16-Jul-15
Completion Date: 10-Jul-2023 (EOT Done)
Project Description
No description available.