Contract Agreement Amount
Rs. 6,04,43,408
Physical Progress
0.00%
Financial Progress
118.04%
Remaining Payment
Rs. -18
Construction of double span simple RCC Bridge over chhepe river padabesi gorkha
Office: गाेरखा सडक योजना, गोरखा (108)
Fiscal Year: 072-73
Contract Date: 14-Jul-16
Start Date: 16-Jul-16
Completion Date: 27-Jun-2021 (EOT Done)