Contract Agreement Amount
Rs. 3,68,42,661
Physical Progress
85.00%
Financial Progress
116.79%
Remaining Payment
Rs. -16
Jitpur- Taulihawa- Khunuwa NH50 Road from Chainage 22+310 to Chainage 30+500, Kapilvastu
Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)
Fiscal Year: 079-80
Contract Date: 30-Sep-22
Start Date: 30-Sep-22
Completion Date: 30-Jun-2023 (EOT Not Done)
Project Description
No description available.