Contract Agreement Amount
Rs. 1,10,81,444
Physical Progress
20.00%
Financial Progress
114.01%
Remaining Payment
Rs. -14
Maintenance of Road, by Construction of Roadway Structures, Humepipe Culverts, Slab Culverts and Earthworks in Bahulabase Khola, Baglung (CH 152+500) to Bhuithan Danda-Harpe, Baglung (CH 158+500) section along Saljhandi-Sandikharka-Dhorpatan Road
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 077-78
Contract Date: 26-Apr-21
Start Date: 26-Apr-21
Completion Date: 04-Jan-2022 (EOT Done)
Project Description
No description available.