Contract Agreement Amount
Rs. 7,25,27,567
Physical Progress
0.00%
Financial Progress
113.76%
Remaining Payment
Rs. -13
Upgrading of Dhodhari Rajapur Sati Road Section (Approach of Karnali Satighat Bridge) Bardiya
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वाके (98)
Fiscal Year: 072-73
Contract Date: 20-Jan-16
Start Date: 4-Feb-16
Completion Date: 16-Oct-2020 (EOT Done)
Project Description
No description available.