Contract Agreement Amount
Rs. 39,24,32,387
Physical Progress
0.00%
Financial Progress
112.15%
Remaining Payment
Rs. -12
Lamosanghu tamakoshi Jiri Road, Lamosanghu Mude section. (Ch: 0+000 to 25+000)
Office: lamoshaghu - Taamakoshi - jiri sadak yojana, sindhupalchowk (164)
Fiscal Year: 071-72
Contract Date: 3-Jun-15
Start Date: 25-Oct-15
Completion Date: 15-Nov-2020 (EOT Done)
Project Description
No description available.