Contract Agreement Amount

Rs. 3,51,95,001

Physical Progress

95.00%

Financial Progress

109.26%

Remaining Payment

Rs. -9

RCC Bridge at badhare khola Gorkha

Office: गाेरखा सडक योजना, गोरखा (108)

Fiscal Year: 074-75

95.00%

Contract Date: 16-Oct-17

Start Date: 16-Oct-17

Completion Date: 13-Apr-2023 (EOT Done)

Project Description

No description available.