Contract Agreement Amount

Rs. 4,19,11,320

Physical Progress

95.00%

Financial Progress

108.16%

Remaining Payment

Rs. -8

Widening Of Existing Road with structural works at Dovan Naya Basti Section(50+000 to 53+000)

Office: उत्तर दक्षिण, कोशी सडक योजना, संखुवासभा (57)

Fiscal Year: 078-79

95.00%

Contract Date: 15-Feb-22

Start Date: 15-Feb-22

Completion Date: 12-Nov-2022 (EOT Not Done)

Project Description

No description available.