Contract Agreement Amount

Rs. 1,03,30,31,452

Physical Progress

100.00%

Financial Progress

107.96%

Remaining Payment

Rs. -7

Upgrading of Keshaliya Chimdi Laukahi Phulchauki Road, Sunsari, Chainage : 6+180 to 30+030

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)

Fiscal Year: 074-75

100.00%

Contract Date: 28-Dec-17

Start Date: 12-Jan-18

Completion Date: 11-Jul-2021 (EOT Done)

Project Description

No description available.