Contract Agreement Amount
Rs. 6,04,39,454
Physical Progress
5.00%
Financial Progress
106.09%
Remaining Payment
Rs. -6
Construction of Pre-stressed RCC Bridge over Chauri Khola along Pokhari Chauri Ward No 1 Ramche- Dudedhunga- Simpani Road, Kavre/ Ramechhap.
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 074-75
Contract Date: 2-Jun-17
Start Date: 2-Jun-17
Completion Date: 01-Jun-2019 (EOT Not Done)
Project Description
No description available.