Contract Agreement Amount
Rs. 2,90,11,80,965
Physical Progress
96.00%
Financial Progress
104.25%
Remaining Payment
Rs. -4
Construction of Four Lane RCC Box Girder Bridge Over Mahakali River
Office: हुलाकी राजमार्ग पुल आयोजना, काठमाण्डौ (74)
Fiscal Year: 073-74
Contract Date: 23-Aug-17
Start Date: 23-Aug-17
Completion Date: 07-Nov-2024 (EOT Done)
Project Description
No description available.