Contract Agreement Amount
Rs. 1,40,80,358
Physical Progress
100.00%
Financial Progress
104.00%
Remaining Payment
Rs. -4
Road Upgrading works along Dumkibas- Dadajor-Sardi- Dhurkot-PalpaSadak, Nawalpur
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 18-May-20
Start Date: 18-May-20
Completion Date: 09-Jul-2020 (EOT Not Done)
Project Description
No description available.