Contract Agreement Amount

Rs. 4,17,91,868

Physical Progress

50.00%

Financial Progress

103.80%

Remaining Payment

Rs. -3

Road Upgarding and Rehabilitation works on Chyamaing Nala Banepa Ch 5+000-11+500

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 076-77

50.00%

Contract Date: 29-Jan-20

Start Date: 29-Jan-20

Completion Date: 09-Jul-2020 (EOT Not Done)

Project Description

No description available.