Contract Agreement Amount
Rs. 3,32,68,131
Physical Progress
19.41%
Financial Progress
102.51%
Remaining Payment
Rs. -2
Rehabiliation of Road in Kalangagad-Chainpur Section of Khodpe- Chainpur Highway (NH-64), Chainage: 60+000 to 108+000
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 078-79
Contract Date: 9-Mar-22
Start Date: 9-Mar-22
Completion Date: 13-Jun-2022 (EOT Not Done)
Project Description
No description available.